warns barriers could delay wind projects by almost three years.
warned that barriers to building onshore wind farms could delay projects by almost three years and cause to miss its renewable energy targets.
The analysis covered 56 projects due to start construction by 2030, with a combined capacity of about 30 gigawatts.
It identified more than 900 constraints for oversized loads on Australian roads; almost half were on national freight routes.
The report called for urgent regulatory changes and freight upgrades to address the barriers.
The story so far 2
- Wind investment falls almost 60% as Australia’s wind rollout stalls.
- You’ve just read thisInfrastructure Australia warns barriers could delay wind projects by almost three years.
Sources 1
Infrastructure Australia is an independent statutory body providing independent research and advice to all levels of government and industry on projects and reforms relating to investment in Australian infrastructure. It advocates for reforms on issues including financing, delivering and operating infrastructure and how to better plan and use Australia's infrastructure networks.
Australia, officially the Commonwealth of Australia, is a country comprising the mainland of the Australian continent, the island of Tasmania and numerous smaller islands. It has a land area of 7,688,287 km2 (2,968,464 sq mi), making it the sixth-largest country in the world, and is the world's flattest and driest inhabited continent. It is a megadiverse country, and its size gives it a wide variety of landscapes and climates, including large deserts centrally and tropical rainforests along the coast.