Australia’s Snowy 2.0 hydro project could cost $25 billion, up from $2 billion.

Snowy 2.0Conquimbo — Own work · CC BY-SA 3.0

’s new cost target is $22.2 billion. The higher scenario includes a $2.8 billion contingency.

Full commissioning has moved to late 2029. The original plan called for completion in 2021.

Machine tunnelling is 65 per cent complete, compared with 19 per cent at the 2023 cost reset.

The government says it will decide how to support Snowy Hydro and add oversight; the company is developing a capital strategy for the new cost.