Wind investment falls almost 60% as Australia’s wind rollout stalls.

In 2025 Australia’s investment in wind plunged to $2.6 billion, down almost 60% and leaving few new wind farms ready to begin construction this year.

At the same time investment in batteries jumped $4.8 billion, up almost 70%, and imports of battery storage roughly quadrupled between 2022 and 2025.

The is counting on wind to supply 47% of renewables’ power in the main grid by 2030, while the federal 82% by 2030 target is now slipping out of reach.

Industry blames supply-chain shortages, financing problems and higher equipment costs, noting turbine prices rose almost 40% between 2020 and 2022 and wind projects take over a year longer to build than solar.

Major coal closures will remove about 30 terawatt-hours a year when Yallourn, Eraring and Gladstone retire, a shortfall that could grow if the wind investment slump continues.

The story so far 2

  1. You’ve just read thisWind investment falls almost 60% as Australia’s wind rollout stalls.
  2. Infrastructure Australia warns barriers could delay wind projects by almost three years.