# Wallan’s $175 million road upgrades are on track to finish six months early.

Published: 2026-10-21 · Location: Wallan, Victoria, Australia · Sources: 3

## Summary

The Watson Street Interchange is more than halfway complete and due to open in mid-2027, six months early.

The interchange will create a full diamond interchange at the Hume Freeway, with more direct connections to Wallan and its East industrial precinct.

The Northern Highway upgrade is also on track to finish six months early, adding lanes in both directions and a second right-turn lane from Watson Street towards Wallan.

The Australian and Victorian governments are jointly funding the projects, which are supporting more than 1,100 jobs during construction.

## Sources

- Mitchell Shire News: [Wallan freeway upgrades on track to finish six months early](https://www.mitchellshire.vic.gov.au/news/wallan-freeway-upgrades-on-track-to-finish-six-months-early)
- Mitchell Shire News: [Monthly Mitchell roads update - October](https://www.mitchellshire.vic.gov.au/news/monthly-roads-update-october-2026)
- Mitchell Shire Council: [Great news for Wallan – major works on the Watson Street Interchange Upgrade are expected to finish…](https://www.facebook.com/MitchellShire/posts/pfbid034EiPjEfQgj1Z1Ho4m3xXYZ4WmJmFMZ2eyU2jaQFc2pkrALPDqmpJCZ371Z6X2A5Dl?__cft__[0]=AZgYwjDZkTaUZzcg9BZPQD98RpZDSjoiQv4hWdlG29oVmSQe7JeFL65q6sWO5XDlFxH_T6xdyrlcyi7WeThCshwwT1rm66jUwjuRYpQGdVcAxIV4ZzOOZ3Tfc91gROAv1ACRiEVfnWNYcIGpF3sdUM1vVk-KJnqUtt0IZzHhCxEio8Kk-HhSGJzFm4qfAgv_YjDU-MII8lZxAILFP6k&__tn__=%2CO%2CP-R)
- Ministers for the Department of Infrastructure: [Wallan upgrades powering ahead of schedule](https://minister.infrastructure.gov.au/c-king/media-release/wallan-upgrades-powering-ahead-schedule)

---

Summary written by Brief (itsbrief.com) from the reporting linked above. Canonical page: https://itsbrief.com/story/wallan-s-175-million-road-upgrades-are-on-track-to-finish-30435746
More Wallan news: https://itsbrief.com/local/wallan