Wagga Wagga residents push back on $15 billion data centre that would use as much power as 1 million homes.

A petition started by locals has attracted more than 1,000 signatures calling to halt a $15 billion data centre campus outside .

CDC Data Centres proposes a 1.4-gigawatt facility on a 100-hectare council-owned site next to the city landfill, about 15 kilometres from the city centre.

The company estimates the campus could use between 1 and 1.5 million homes' worth of electricity each year, about 5-7 TWh annually at 40–60% operation.

Only a scoping report has been released so far; once the state sets requirements CDC will have two years to submit a full Environmental Impact Statement covering power, noise and water.

The company says stage-one would need an initial fill of 1.28 million litres of water and annual use of 1,512,000 litres per year; the first community consultation sessions are scheduled for next week.