← Back to Feed
Victoria· 18d

’s mental-health IT system faces a two-year delay.

The system was originally due by June 30 this year, but the government dashboard now advertises completion in June 2028.

The project’s planned cost was listed as $40.23 million; its allocation is now $64.7 million.

Leaked project documents say the upgrade is not yet compatible with services of high digital maturity, including public hospitals.

A trial is expected to begin later this year at a service with low digital maturity; the first implementation is planned for late 2026, with statewide delivery scheduled for mid-2028.