The Fair Work Commission hears its first Net Zero law case on power-station worker support.
The began its hearing in this week over support for more than 100 workers expected to lose their jobs when Torrens Island B closes in June 2028.
Unions are seeking a total of $33,500 per worker, plus paid time off for training, advice and job interviews.
has proposed a $7,500 cap per worker for training and financial advice.
The decision is likely to shape how other power-station closures handle workforce redundancies, with workers at and expected to watch closely.
Sources 2
About
Adelaide is the capital and most populous city of South Australia, as well as the fifth-most populous city in Australia. The name "Adelaide" may refer to either Greater Adelaide or the Adelaide central business district; the demonym Adelaidean is used to denote the city and the residents of Adelaide. The traditional owners of the Adelaide region are the Kaurna, with the name Tarndanya referring to the area of the city centre and surrounding Park Lands, in the Kaurna language. Adelaide is situated on the Adelaide Plains north of the Fleurieu Peninsula, between the Gulf St Vincent in the west and the Mount Lofty Ranges in the east. Its metropolitan area encompasses over 430 suburbs, extending 96 km (60 mi) from Gawler in the north to Sellicks Beach in the south and 20 km (12 mi) from the western coast to the eastern foothills of the Mount Lofty Ranges.
About
AGL Energy Ltd is an Australian listed public company involved in both the generation and retailing of electricity and gas for residential and commercial use. It is one of the "big three" retailers in the National Electricity Market. AGL is Australia's largest electricity generator, and the nation's largest carbon emitter.
About
Eraring Power Station is a coal-fired power station consisting of four 720 MW Toshiba steam-driven turbo-alternators for a combined capacity of 2,880 MW. The station is located near the township of Dora Creek, on the western shore of Lake Macquarie, New South Wales, Australia and is owned and operated by Origin Energy. It is Australia's largest power station. The plant has two smokestacks rising 200 m (656 ft) in height. It was scheduled for closure by mid-2025, after a failed attempt to sell the loss making power station back to the state government but had its life extended twice, now commissioned until April 2029.
About
The Yallourn Power Station, now owned by EnergyAustralia is located in the Latrobe Valley of Victoria, Australia, beside the Latrobe River. Yallourn Power Station was a complex of six brown coal–fired thermal power stations built progressively from the 1920s to the 1960s; all except one have now been decommissioned. Today, only the 1,450-megawatt (1,940,000 hp) Yallourn W plant remains. It is the second largest power station in Victoria, supplying about 7.8TWh in 2025, or around 15% of Victoria's electricity and 4% of the National Electricity Market.
The Fair Work Commission began hearing its first case under Net Zero laws regarding support for workers at a closing power station.This story
The High Court rejected Uber's appeal on payroll tax obligations following a Fair Work Commission ruling on minimum pay for food delivery workers.→ 11 NovAbout
The Fair Work Commission (FWC), until 2013 known as Fair Work Australia (FWA), is the Australian industrial relations tribunal created by the Fair Work Act 2009 as part of the Rudd Government's reforms to industrial relations in Australia. Operations commenced on 1 July 2009. It is the successor of the Australian Industrial Relations Commission, and also performs functions previously performed by the Workplace Authority and the Australian Fair Pay Commission.