← Back to Feed
Business & money Australia· 8h

Stadium CEO rejects claims Hobart project will cost nearly $2 billion.

Anne Beach, the CEO of Hobart’s stadium project, rejected claims its true cost is closer to $2 billion and outlined expected construction progress. 

The government’s latest estimate is $1.545 billion, up from $1.13 billion last year. It shared the increase earlier this week, and Tasmania’s parliament debated the new costs after Tuesday’s update. 

Seven had asked the premier and treasurer to publish all stadium costs before signing a building contract, in an open letter on November 23. 

Work has started at the site, including archaeological investigations to remove material. Within 12 months, excavation is expected to be complete and the construction company ’s team is expected to be working on site. 

The project expects plans and approvals to be resolved and construction to be visibly progressing around the middle of next year. The stadium is now believed to be targeted for completion in the 2031 season. 

The story so far 4

  1. Tasmania raises stadium estimate to $1.23 billion and drops its $875 million cap.
  2. You’ve just read thisStadium CEO rejects claims Hobart project will cost nearly $2 billion.

Sources 1

‹ Back to your Brief