Shared paths in Braybrook and Sunshine will close for Melbourne Airport Rail works.
Sections of shared paths in Braybrook and Sunshine will close from 5 November for underground electricity and telecommunications works connected with .
In Braybrook, the path between Holzer Crescent and Teague Crescent will be closed 24 hours a day until 22 December; cyclists will detour via Royal Road and Teague Crescent.
The Sunshine path closure, near , is scheduled to last until mid December, with detours in place.
Work is planned Monday to Friday, 7am to 6pm, with Saturday work possible from 7am to 1pm if required.
Sources 2
- M
Maribyrnong Council Elections
BRAYBROOK SHARED PATH CLOSURE 5 November to 22 December 2026
↗ - M
Maribyrnong Council Elections
The shared path between Holzer Crescent and Teague Crescent, near Braybrook Grasslands, will be closed 24 hours a day during this period
↗ - M
Maribyrnong Council Elections
Cyclists will be diverted via Royal Road and Teague Crescent
↗
- M
Maribyrnong Council Elections
SUNSHINE SHARED PATH CLOSURE 5 November to mid December 2026
↗ - M
Maribyrnong Council Elections
A section of the shared path near Drayton Street and Station Place, close to Sunshine Station
↗ - M
Maribyrnong Council Elections
will also be closed for telecommunications works, with detours in place
↗
About
Sunshine railway station is a railway station operated by Metro Trains Melbourne and V/Line on the Sunbury, Geelong and Ballarat lines, serving the western suburb of the same name in Melbourne, Victoria, Australia. The station opened on 7 September 1885, with the current station opening in 2014, after reconstruction as part of the Regional Rail Link project.
About
Melbourne Airport Rail is an under-construction heavy rail airport mass transit link project connecting the Melbourne central business district to Melbourne Airport in Tullamarine. The rail link will run through the existing Sunbury line and Metro Tunnel, running 27 km (16.8 mi) from the airport to Town Hall station in the Melbourne city centre with 12 km (7.5 mi) of new track between the airport and Sunshine station. The project is being delivered by the Victorian Infrastructure Delivery Authority through the Level Crossing Removal Project.