# Power company pauses five-storey pole rollout after Melbourne council says no permits.

Published: 2026-09-14 · Location: Maribyrnong, Victoria, Australia · Sources: 1

## Summary

Jemena began installing five-storey concrete power poles in Melbourne's Yarraville, West Footscray and Tottenham. After resident outcry and council objections, the rollout was paused earlier this month.

The council says the company had no approval to work in road reserves — footpaths, nature strips and gutters. "Those permits were not approved," said mayor Mohamed Semra.

The 15-metre poles, almost twice the height of wooden ones, are built to handle higher electricity demand, including from data centres.

Jemena said it "paused the works program" to engage with stakeholders and review its approach. The company gave no timeline for resuming work or comment on the council's permission claim.

Maribyrnong City Council will invite ministers and energy authorities to visit the area and see the poles' impact first-hand.

## Sources

- Star Weekly - Maribyrnong & Hobsons Bay News: [No permission for power poles](https://maribyrnonghobsonsbay.starweekly.com.au/news/no-permission-for-power-poles/)

---

Summary written by Brief (itsbrief.com) from the reporting linked above. Canonical page: https://itsbrief.com/story/power-company-pauses-five-storey-pole-rollout-after-2b32f414
More Maribyrnong news: https://itsbrief.com/local/maribyrnong