audit finds $63.7 million in facilities cut from hospital project.

Albury-WodongaWongm — Own work · CC BY-SA 3.0

The $558 million redevelopment was budgeted before its full needs and costs were known, the audit found. 

The cuts removed a paediatric unit, operating theatres and a helipad; the theatres and paediatric spaces were left as cold shells, without power, plumbing, ceilings or clinical fitouts. 

The audit found hospital-building budgets were routinely approved before preliminary or full business cases were developed, and made six recommendations for implementation by November 2027. 