# Jacinta Allan’s 2022 election delay adds $16.5 million to Glen Huntly rail project.

Published: 2026-11-24 · Location: Australia · Sources: 2

## Summary

When Jacinta Allan was transport infrastructure minister, she delayed planned express-track closures on Melbourne’s Frankston line until after the November 2022 state election. The change added $16.5 million to the Glen Huntly level-crossing removal project.

The original contracts called for the express track to close from July 2022 until June 2023. Frankston-line services would then stop at every station, adding up to 10 minutes to journeys into the city.

The closures were pushed back to December 2022 to keep express trains running from September to November. Builders had to work more nights and weekends, pay penalty rates and arrange more temporary relocations because of construction noise.

The transport department first estimated the change would cost between $22 million and $28 million. Allan’s spokesman said she accepted advice to reduce disruption for passengers while keeping the project on course.

## Sources

- The Age: [Exclusive: Documents show Jacinta Allan ordered level crossing works delayed to keep Frankston…](https://www.facebook.com/theageAustralia/posts/pfbid0pUByHDwh2DyDtxRJ8yGEz8ZyDCTNYox4F4f8AWe8WhTUYCjB1JDWZc6LoNU7cMhdl?__cft__[0]=AZhaealX2SPlVvq7EKXLHWTgWMx_TFyEgqi3cZRfTSvzcwqXMX-BjiMxH6gsZFWQMC2n4j7BXU5hAnGes3_-zH2LAD3Y3H6c4XR9mI1wNMbA4ge9Paa7tIFKMpEn5J51H3YICKBlghV30NnvUzy55Y-krvNsGV3Ak34pfpvSmw86cILyCe2kfttvma0&__tn__=%2CO%2CP-R)
- The Age - Business: [Allan’s election express: Rail project delay call cost taxpayers $16.5m](https://www.theage.com.au/politics/victoria/allan-s-election-express-rail-project-delay-call-cost-taxpayers-16-5m-20261125-p61gu7.html)

---

Summary written by Brief (itsbrief.com) from the reporting linked above. Canonical page: https://itsbrief.com/story/jacinta-allan-s-2022-election-delay-adds-16-5-million-to-cc10563f