Inland Rail reopens Broadford bridge giving double-stacked freight clearance.

demolished the old Marchbanks Road bridge and opened a single lane on the new structure, restoring motorists’ access to the after an eight-week closure.

The new bridge is 3.7 metres higher and 11 metres wider than the former structure, which enables double-stacked freight trains to pass through.

Marchbanks Road is the last bridge replaced on the -to- section, and Inland Rail has now achieved the required clearances at 11 of 12 sites on that route.

Inland Rail says short-term temporary bridge closures may still be needed to finish final construction, and local authorities warn of further roadworks and traffic changes including closures in Wandong from 14 to 28 October.